The following statements' relate to project network. Choose the correct answer for the statements being correct or-incorrect.<br>Statement I An activity cannot be represented by more than one arrow, but. an arrow can represent one or more activities.<br>Statement II The activities in a critical path can be preponed or postponed.

Correct Answer: Both statements are incorrect