Statement I The critical path has been defined as the longest duration path between the first and the last nodes of a project.<br>Statement II The duration of a project is not always the same as the duration of its critical path.<br>Statement III The earliest start and finish times of an activity are based on the condition that every activity will not be started and finished as early as possible.<br>Find the correct answer for given statements being correct or incorrect.

Correct Answer: Statement I is correct, but Statements II and III are not correct