From the given below statements, find the incorrect statement. i. A critical path has zero float. ii. A critical path has both critical and non-critical activities. iii. A critical path is the longest path and consumes maximum time and resources.

Correct Answer: ii only
A Critical path always has zero float. Critical path will have only critical activities which upon delayed will delay the entire project. A critical path is the longest path and consumes maximum time and resources.