The following project network is given with arrows as activities and the numbers by each arrow representing job durations in days. The network has two dummy activities D<sub>1</sub> and D<sub>2</sub>. The minimum completion time of the project in days is<br><img src="/images/question-image/mining-engineering/mine-system-engineering/1682420921-M2-7-23-20.PNG" title="Mine System Engineering mcq question image" alt="Mine System Engineering mcq question image">

Correct Answer: 68