In the project network shown activity durations are given in months. If the activity can be crashed to expedite the project, which one would you crash and by how many months?<br><img src="/images/question-image/mining-engineering/mine-system-engineering/1682421105-M2-7-24-21.PNG" title="Mine System Engineering mcq question image" alt="Mine System Engineering mcq question image">

Correct Answer: C, 1