A and B can complete a task in 1.5 days. However, A had to leave a few days before the task wascompleted and hence it took 2 days in all to complete the task. If A alone could complete the work in2.625 days, how many days before the work getting over did A leave?
A
1.125
B
0.625
C
0.375
D
0.875
Correct Answer:
0.875
A and B can complete a task in 12 days. However, A had to leave a few days before the task was completed and hence it took 16 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?
A
7
B
5
C
9
D
3
Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing 1/3 of the task. Then, Sharan takes over and completees the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayuk' had worked faster than Sharan ?
A
24
B
45
C
72
D
30
Directions: Four friends Raghu, Rajesh, Ramesh and Ravi complete their Graduation in different number of years. The one who took maximum time took eight years to complete his Graduation while the one who took least time took only three years to complete it.Ravi took more time only than Raghu and completed his Graduation in five years. Ramesh did not take longer time
than Rajesh to complete his Graduation. Question: Who took more years to complete his graduation among all ?
A
Ramesh
B
Raghu
C
Rajesh
D
Ravi
If Arif works alone he will take 20 more hours to complete a task than if he works with Babu to complete the task. If Babu work alone, he will take 5 more hours to complete the task than if he works with Arif to complete the task. What is the ratio of the time taken by Arif to than taken by Babu if each of them works alone to complete the task?
A
2 : 1
B
5 : 3
C
7 : 5
D
None of these
Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the if she worked alone ? Assume that Sudha is more efficient than Asha.
A
25 days
B
30 days
C
60 days
D
65 days
A alone can complete a piece of work in 18 days and B alone in 15 days, B alone worked at it for 10 days and then left the work. In how many more days, will A alone complete the remaining work ?
A
5 days
B
$${\text{5}}\frac{1}{2}{\text{ days}}$$
C
6 days
D
8 days
A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and competes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
A
18
B
22
C
20
D
15
A and B together can do a piece of work in 10 days. If A can do the work in 15 days, find in how many days that B alone can do the same work. Given below are the steps involved in solving the above problem. Arrange them in sequential order. A) One day's work of B is 1/10 - 1/15 B) One day's work of A and B is 1/10 and One day's work of A is 1/15 C) B alone can do the work in 30 days D) One day's work of B is 1/30
A
BADC
B
ADCB
C
BCAD
D
BDAC
A can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?
A
36
B
32
C
40
D
30
Amit can do a piece of work in 45 days, but Bharath can do the same work in 5 days less, than Amit, when working alone. Amit and Bharath both started the work together but Bharath left after some days and Amit finished the remaining work in 56 days with half of his efficiency but he did the work with Bharath with his complete efficiency. For how many days they had worked together?
A
6
B
8
C
9
D
12