Which of the following can help apply the efforts of non-critical activities on critical activities to reduce the project duration?

Correct Answer: Independent float
Independent float can be used to apply the efforts of non-critical activities on critical activities to reduce the project duration. Independent float does not affect the floats of other succeeding or preceding activities.