Only increase in labour cost beyond 2% should be brough to the notice of management which principle of control is this?
(a) Critical point control (b) Control by exception (c) Budgetary control (d) None of these.
A. (a) Critical point control
B. (b) Control by exception
C. (c) Budgetary control
D. (d) None of these.


Share with your friends
Call

Correct Answer - (b) Control by exception