- heterogeneous relationship
- extreme relationship
- no homogeneous relationship
- homogeneous relationship
Answer: Option 4 The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as Dummy
1 Answers 1 viewsAnswer: Option 3 Let'
1 Answers 1 viewsAnswer: Option 1 Total costs in the short-term are classified into fixed costs and variable costs. Cost of raw material is a variable cost. Variable costs vary based on the...
1 Answers 1 viewsAnswer: Option 2 Weak relationship between cost and cost driver is indicated on a regression line, which is slightly sloped.
1 Answers 1 viewsAnswer: Option 2 An assumption, which states that there must be linear relationship between independent variable and dependent variable is relevant range of linearity.
1 Answers 1 viewsAnswer: Option 2 Cost pool category, which have similar cause and effect relationship, with each cost driver uses as an allocation base is classified as homogenous cost pool. A cost...
1 Answers 2 viewsAnswer: Option 1 Hierarchy which is based on different types of cost allocation and drivers, is to categorize cost pool activity is classified as cost hierarchy. The cost hierarchy...
1 Answers 1 viewsAnswer: Option 2 Cost of operating activity, facility or any cost object which usually shares by two or more than two users is classified as common cost. A common...
1 Answers 1 viewsAnswer: Option 2 Method which divides support department cost into two dimensions such as fixed and variable cost pool is classified as dual-rate cost-allocation method. Allocations are performed in order...
1 Answers 1 viewsAnswer: Option 4 Difference of cost, which occurs while considering alternatives can be classified as differential cost. Differential cost is the difference between the cost of two alternative decisions, or...