B would have taken 10 hours more than what A would have taken to complete a task if each of them worked alone. Working together they can complete thetask in 12 hours. How many hours would B take to do 50% of the task?
A
30
B
15
C
20
D
10
Correct Answer:
15
If Arif works alone he will take 20 more hours to complete a task than if he works with Babu to complete the task. If Babu work alone, he will take 5 more hours to complete the task than if he works with Arif to complete the task. What is the ratio of the time taken by Arif to than taken by Babu if each of them works alone to complete the task?
A
2 : 1
B
5 : 3
C
7 : 5
D
None of these
Two men and women are entrusted with a task. The second man needs three hours more to cope up with the job than the second man and the woman would need working together. The first man, working alone, would need as much time as second man and the woman working together. The first man working alone, would spend eight hours less than the double period of the time second man would spend working alone. How much time would the two men and the women need to complete the task if they all asked together?
A
1 hour
B
2 hours
C
3 hours
D
4 hours
E
5 hours
Three friends Anne, Bob and Chris work together to do a certain job. Time it takes them to do the work together to do a certain job. The it takes them to do the work together is 6 hours less than Anne would have take alone, 1 hour less than Bob would have taken alone and half the time Chris would have taken working alone text. How long did it take them to complete the job, working together ?
A
20 minutes
B
30 minutes
C
40 minutes
D
50 minutes
Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 4
1
/
2
hours more to complete the job than they both working together. What time would they take to do the work together ?
A
4 hours
B
5 hours
C
6 hours
D
7 hours
Meghana alone would take 32 hours more to complete a job than both Meghana and Ganesh together. If Ganesh worked alone, he took 12 1/2 hours more to complete it than both Meghana and Ganesh worked together. What time would they take if both Meghana and Ganesh worked together?
A
20 hrs
B
18 hrs
C
22 hrs
D
20.5 hrs
Tow workers A and B are engaged to do a work . A working alone takes 8 hours more to complete the job than if both worked together . If B worked along, he would need 4.5 hours more to complete the job than they both working together . What time would they take to do the work together ?
A
4 hours
B
5 hours
C
6 hours
D
7 hours
Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take $$\frac{8}{3}$$ more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?
A
2 days
B
4 days
C
6 days
D
8 days
E
10 days
A, B and C can complete a task together in 10 days. A and B would need 12 days if only the two of them worked, while B and C would take 20 days if only the two of them worked. If B worked alone, how many days would she take to complete the task?
A
30
B
22
C
45
D
20
Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the if she worked alone ? Assume that Sudha is more efficient than Asha.
A
25 days
B
30 days
C
60 days
D
65 days
Two worker A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take $${\text{4}}\frac{1}{2}$$ hours more than when working together. The time required to finish the work together is = ?
A
5 hours
B
8 houras
C
4 hours
D
6 hours