15 men can do a piece of work in 17 days, working 7.5 hours daily. Find the time in which 11 men can do the same work, working 2.1 hours daily.

Correct Answer: 88 days
The total amount of work done = 15 * 18 * 7.5 = 2025 units The number of men available = 11 The daily working hours = 2.1 hour Number of days taken = 2025 / (11 * 2.1) = 87.66 days